The Confluence development team always knows its status relative to plan. At the end of each week, the team updates the issues table below to show which issues were addressed and which ones carried over. The team also uses the {chart} macro to create a burndown chart showing how much work is left relative to how much time is left.

  • Edit this page and change one of the numbers in the chart. Save or preview the page to see your changes.
  • Edit this page and update the status one of the rows by (like "quick-nav: selenium testing") by adding a (tick) to the status column.

Burndown chart

The following graph provides a rough status on the progress of the Confluence team.

 

1

2

3

4

5

6

7

8

9

10

Confluence 2.10

23

21

16.5

14

13

11.5

9.5

8

9

7.25


Rules for how to update the release dashboard:

Steps that need to be done at the end of an iteration

2.10 is estimated to be a 3 month release, manned by a 2 person team (with one person doing part time bug fixing). Accounting for 1 week of sick or holiday leave, we have a feature budget of 14u (11 iterations).

Iteration

Week 1: 30/JUL

Estimate

Remaining at very start of release cycle: 23

1

Discovery feature breakdown

1u

(tick)

 

Remove SearchService

1u

(tick)

 

Investigate/rework did-you-mean indexing

1u

(tick)

 

Deploy RC1 to QA and Production

1u

(tick)

 

Week 2: 6AUG

4u

Velocity: 4u. Remaining: 21

2

Make author filter work for external users (CONF-10769)

2u

(tick)
 

 

Quick search by page title task breakdown

1u

(tick)

 

Respond to Did-You-Mean review feedback

1u

(tick)

 

Add author filter to people directory

1u

Decided to discontinue work on card after 0.5u investigation.

 

Week 3: 13/AUG

4u

Velocity: 5u. Remaining:  16.5u

3

Make author filter work for hosted

2u

(tick)

 

Fix archiva with James

0.5u

(tick)

 

Discovery planning


(tick)

 

Code reviews 


(tick)

 

Week 4: 20/AUG

4.5u

Velocity: 2.5u. Remaining: 14u

4

quick-search-by-title: Add lucene index fields

1u

 

 

Week 5: 27/AUG

1u

Velocity: 1u. Remaining: 13u

 

did-you-mean: merge to trunk  

0.5u

(tick)

 

did-you-mean: run clover and add tests

1u

(tick)

 

Week 6: 3/SEP

1.5u

Velocity: 1.5u. Remaining: 11.5u

 

quick-search-by-title: backend

2u

(tick) Carried over twice from previous iteration, took longer than expected

 

Week 7: 10/SEP

2u

Velocity: 2u. Remaining: 9.5u

 

quick-search-by-title: JSON

0.5u

(tick) Carried over from previous iteration

 

quick-search-by-title: UI Integration

1u

(tick) Carried over from previous iteration

 

search-visuals: clean up display of individual results

2u

(tick)

 

Week 8: 10/SEP

3.5u

Velocity: 3.5u. Remaining: 8u

 

quick-nav: bug fixes (unicode, themes, highlighting)

1u

(tick)

 

Week 9: 17/SEP

1u

Velocity: 1u. Remaining: 11u

 

quick-nav: selenium testing

1u

 

 

search-visuals: Add people thumbnails to search results

1u

 

 

Week 10: 24/SEP

2u


 

did-you-mean: indexing issues (CONF-12943)

1u

 

 

Week 11: 6/OCT

1u


 

quick-search-by-title: Advanced JS component

  • IE bug (CONF-13158)
  • density and organisation
  • Caching issues

3u


 

quick-nav: performance testing 

1u


 

quick-nav: Timouts (CONF-13062)

1u


 

Week 12: 13/OCT

4u


 

OpenSearch plugin (advertisement only)

0.5u

 

 

quick-nav: Document for custom layouts (CONF-13073)

0.25u

 

 

Week 13: 20/OCT

0.75u


Dropped from release

 

quick-nav: relevancy: boost by favourites

2u

(not counted for remaining estimate, since originally unplanned and not in current plan anymore)

 

search-visuals: Adjust number of results per page

1u

 

 

Change default space content

0.5u

 

 

did-you-mean: auto-enable for english customers (CONF-13209)

1u

 








This is sample content that comes included with Confluence for the purposes of demonstrating how the product can be used.